JCM delivered the core and shell mechanical and plumbing systems serving 1 MM SF of new trophy office space. The systems included a 3500 ton chiller plant with distribution to an 11 story garage and two separate towers totaling 22 and 29 stories, along with over 1400 fan powered terminal boxes and 32 air handling units. JCM delivered this $45MM project on schedule, despite bulk construction occurring in the height of the COVID-19 pandemic.