CFG Bank Arena

Baltimore, MD

Design AssistHospitality

Delivering a gut renovation and complete overhaul of a 14,000 seat stadium venue in only 10 months is no small feat. JCM delivered new HVAC and plumbing systems throughout including city-supplied steam heat generation, chilled water, and 2-story custom DOAS units. The stadium features over 20 food/bar counter outlets, and large bathrooms with over 200 stalls. ​ At the Owner’s request, and to deliver the project on time for an NCAA basketball tournament, JCM accelerated the work, surging to a 125 person plumbing and mechanical crew and working 6 days a week July through Christmas. ​

Owner

Oak View Group

Architect

SCI

MEP Engineer

ME Engineers

Size

400,000 sqft

General Contractor

Clark Construction

Property Location

CFG Bank Arena

Baltimore, MD