Baltimore, MD
Delivering a gut renovation and complete overhaul of a 14,000 seat stadium venue in only 10 months is no small feat. JCM delivered new HVAC and plumbing systems throughout including city-supplied steam heat generation, chilled water, and 2-story custom DOAS units. The stadium features over 20 food/bar counter outlets, and large bathrooms with over 200 stalls. At the Owner’s request, and to deliver the project on time for an NCAA basketball tournament, JCM accelerated the work, surging to a 125 person plumbing and mechanical crew and working 6 days a week July through Christmas.
Property Location
CFG Bank Arena
Baltimore, MD